"Construction of Eight Lane Vadodara Kim Expressway from Km 323.00 to Km 355.00 - Sanpa to Padra Section of Vadodara Mumbai Expressway in the State of Gujarat under NHDP Phase - VI on EPC mode." (The Project).

Project At
Glance.

Bid Project Cost :-
Rs. 1464.99.00 Cr.
Project Start Date :- 31.01.2019
Project execution period :- 22 Months
Operation & Maintenance :- 4 Years
Length of the Project Highway :- 32.00 Km
Client :- National Highways Authority of India (NHAI)
Concessionaire :- IRCON Vadodara-Kim Expressway Limited
EPC Contractor :- Ircon International Ltd
EPC Sub-Contractor :- Patel Infrastructure Limited
Independent Engineer :- M/s Aarvee Associates Architects Engineers & Consultants Pvt. Ltd.,

Proposal for Improved Connectivity.

The total length of the project is 32.000 Kms. The Scope of the Project Construction of Eight Lane Vadodara Kim Expressway from Km 323+000 to Km 355+000 (Sanpa to Padra Section of Vadodara Mumbai Expressway) with development of new Greenfield alignment. The expressway comprises of Rigid pavement for Main Carriageway and Flexible pavement for the Connecting road. The Project road under Phase lA-Package II starts at Km 323+000 near Sanpa of Karjan Taluka. The Expressway alignment runs almost parallel to existing NH 8 on west side.

Project
Time Line.

29/10/2018
Letter Of Award

19/11/2018
Agreement

31/01/2019
Financial Closure

31/01/2019
Appointed Date

25/08/2022 Provisional Completion Date as per EOT

DL & M
Period 4 Years

Existing Project Site.

National Highways Development Project (NHDP) Phase-VI is for development of 1000 km of expressways and includes construction of about 379 km long Vadodara-Mumbai Expressway proposed to be implemented under Public Private Partnership mode and to be executed as Design, Build, Finance and Operate (DBFO) contracts. The proposed Main Expressway passes through the states of Maharashtra, Gujarat and Union territory of Dadra & Nagar Haveli. The total length of the proposed expressway is about 379 km and runs generally parallel to the existing NH-8.

The Project Expressway Package II of the Expressway traverses through Bharuch districts viz. starts from Sanpa Km 323.00 and ends at Padra Km 355.00 near Vadodara in the state of Gujarat.

map

MONTHLY PROGRESS REPORT.

No. Month Remarks
1 Mar-19        
2 Apr-19        
3 May-19        
4 Jun-19        
5 Jul-19        
6 Aug-19        
7 Sep-19        
8 Oct-19        
9 Nov-19        
10 Dec-19        
11 Jan-20        
12 Feb-20        
13 Mar-20        
14 Apr-20        
15 May-20        
16 Jun-20        
17 Jul-20        
18 Aug-20        
19 Sep-20        
20 Oct-20        
21 Nov-20        
22 Dec-20        
23 Jan-21        
24 Feb-21        
25 Mar-21        
26 Apr-21        
27 May-21        
28 Jun-21        
27 Jul-21